Emergency Boiler Repair

client icon Client: Teck-Cominco

location icon Location: Trail, BC

An explosion in the KIVCET boiler in February 2004 caused the Lead South operations to go offline. Balanced Power engineers were onsite within days, evaluating the boiler damage and preparing a repair scope of work.

Providing engineering support to CIMS, Balanced Power was involved in the rapid repair of the boiler, allowing restart within 40 days of the failure. The quick response to the shutdown during a period of high metal prices minimized losses for the company.